HALLEFREAKINLUJAH!!!!

at LONG last, something that resembles building!  ICF (Insulated Concrete Forms – R24) foundation walls to follow this week….sub-slab utility rough-in next week….pour slab the week of july 24 (or, so we hope!).  then, arrival of the SIPs building shell and triple-glazed windows in early to mid-august.  so, by end of august we could (should?) have a building shell!

discussion of foundation details, especially in reference to energy-efficient design and construction methods forthcoming.